A monorail system is a single overhead beam that carries a trolley and hoist along a fixed path, and a conveyor system moves material along frames, stringers and overhead supports. Both depend on structural steel: S-beams or W-beams for monorail track, and channels, angles, tube and plate for hangers, conveyor legs, headers, platforms and bracing.
What sets this steel apart from ordinary building framing is that equipment runs on it or hangs from it. Track joints must be smooth, hanger holes must line up with building steel, and the structure has to carry moving loads every day for decades.
Monorail track and its steel
Monorail track comes in three main forms. The choice depends on capacity, span, trolley design and how often the system will be changed.
| Track type | Description | Notes |
|---|---|---|
| S-beam (American Standard beam) | Hot rolled I-shape with sloped inner flanges | Traditional monorail section; trolley wheels are matched to the flange slope |
| W-beam (wide flange) | Hot rolled I-shape with parallel flanges | Wider flanges for heavier loads; trolleys need flat tread wheels |
| Patented track | Proprietary track, often with a hardened running flange | Built and rated by the track manufacturer as a system |
The inner faces of S-beam flanges slope at about 16-2/3 percent (2 in 12), while W-beam flanges are parallel, so trolley wheels made for one do not seat properly on the other. Confirm the beam type and the trolley model together before the track is ordered.
Beyond the track itself, a monorail system includes hangers or rigid supports, sway bracing, splice plates, end stops and sometimes curves, switches and interlocks where it crosses or joins other runways.
Standards for monorails and underhung systems
- ASME B30.11 and B30.17. The ASME B30 safety standards cover construction, installation, inspection, testing, maintenance and operation of monorails and underhung cranes. B30.11 has long covered monorails and underhung cranes, and recent editions of B30.17 address cranes and monorails with underhung trolleys, so check which edition the project or owner references.
- ANSI MH27.1. Published by the Monorail Manufacturers Association, this specification covers patented track underhung cranes and monorail systems.
- CMAA 74. The Crane Manufacturers Association of America specification for top running and under running single girder cranes with under running trolley hoists, often used alongside monorails in the same building.
- AISC 360 and runway design guidance. Rolled beam monorails and their supports are designed as structural steel to AISC 360, and AISC Design Guide 7 is a common reference for crane runways. Local bending of the lower flange under trolley wheel loads often governs monorail beam size; CMAA 74 gives a method for checking it.
The B30 standards call for the rated load to be marked on the system and for new or altered monorails to be load tested before use. These are the owner’s and installer’s responsibilities, but they explain why accurate, documented fabrication matters.
Fabricating monorail track and supports
Track beams and splices
Track beams are sawn square to length and drilled for splice plates and hanger connections, the same beam drilling and coping work used on building steel. At every splice the lower flanges, which form the running surface, must be flush and aligned so trolley wheels roll across without a bump. Splices are typically detailed with plates that clamp or bolt both beams and keep the running flanges clear of bolt heads.
Hangers and supports
Monorails hang from building steel by rod hangers with beam clamps, or by rigid hangers made from angle, channel or tube with welded plates. Rigid hangers and sway bracing limit swinging when the hoist starts and stops. Hanger holes must match the building beams they connect to, so dimensions should be field verified or taken from the building’s as-built drawings.
End stops and attachments
End stops bolt or weld to the track to keep the trolley from running off the end. Their design and location come from the system designer, and they must not interfere with the trolley’s wheels or side guides.
Straightness
ASTM A6 sets mill tolerances for camber and sweep of rolled shapes. A track that must run smoothly may need straightness tighter than mill tolerance, which affects material selection and processing, so the drawing should state the requirement if one applies.
Tip: Match mark each track splice in the shop and ship pieces in installation order. Track sections fitted in the order they were checked go up faster and with fewer adjustments at the joints.
Conveyor support structures
Conveyors are covered by ASME B20.1, the safety standard for conveyors and related equipment, and bulk and unit handling conveyors are often built to Conveyor Equipment Manufacturers Association (CEMA) standards. The conveyor maker usually supplies the conveyor itself, while the support steel is fabricated separately.
- Floor supports. Legs from angle, channel or square tube with base plates, knee braces and cross ties, set at spacing given by the conveyor maker.
- Overhead supports. Headers spanning between building beams or columns, with hangers and sway bracing below. Hanging new conveyor loads from existing roof joists or beams needs review by the building’s engineer, since joists in particular have limited capacity for concentrated loads.
- Galleries and trusses. Bulk material conveyors crossing yards or between buildings ride on steel trusses or galleries supported by bents or towers.
- Platforms and walkways. Maintenance access along conveyors, with grating or tread plate, ladders and guardrails. OSHA 29 CFR 1910.29 sets guardrail top rail height at 42 in (1,067 mm), plus or minus 3 in (76 mm), for general industry.
Our guide to structural steel for commercial construction covers the bolted connections and hole sizes these supports share with building framing.
Processing steps and ordering tips
Most monorail and conveyor steel moves through the same steps as other structural work: sawing and miter cutting, beam drilling and coping, plasma or oxy-fuel cutting of plates and clamps, angle punching, welding and coating. A few habits make orders go smoothly:
- Send drawings that show beam type and size, hole sizes and locations, splice details and any straightness requirement.
- Identify which surfaces are running surfaces so they are kept free of weld spatter, marks and coating build-up where the trolley maker requires.
- Group hanger and leg parts by elevation or area, and mark each with its piece number.
- Specify the finish: shop primer, paint, powder coat or galvanizing, noting that galvanizing on running flanges may need the trolley maker’s approval.
- Ask for mill certifications with the order if the owner’s documentation package requires them.
Monorail and conveyor steel from ASA
American Steel & Aluminum stocks A36 and A992 structural shapes, angle, channel and structural tube, and processes them to customer drawings with sawing, beam drilling and coping, angle punching, plasma and oxy-fuel plate cutting and welding. Beam processing at West Bath, ME runs on a Voortman V807M coping system in a rail served facility with 22-ton cranes, and Saco, ME runs a heavy plate and structural shop. Mill certifications and full material traceability are available; see our steel processing capabilities or call 1-800-933-7833.
Frequently asked questions
What type of beam is used for a monorail?
Traditional monorails run on S-beams, also called American Standard beams, whose sloped inner flanges match tapered trolley wheels. Heavier systems often use wide flange W-beams with flat tread wheels, and many light to medium systems use patented track with a hardened running surface. The beam type, size and trolley model must be selected together by the system designer.
What is the difference between a monorail and an underhung crane?
A monorail is a single fixed track beam, so the hoist travels along one path only. An underhung crane has a bridge girder that rides on two or more runway beams, letting the hoist cover a rectangular area. Both hang from building structure and are covered by the ASME B30 safety standards, and many buildings combine the two.
Can a monorail hang from existing roof joists?
Sometimes, but only after the building's structural engineer has checked the joists or beams for the added moving load, impact and sway forces. Open web steel joists in particular have limited capacity for concentrated loads hung from their chords. In many cases new headers or support steel spanning between primary beams or columns are added to carry the monorail.
Why must monorail track splices be flush?
The bottom flange of a monorail beam is the running surface for the trolley wheels. A step or gap at a splice causes wheels to bump, which adds impact load, wears wheels and track, and can make the hoist swing or bind. Splices are aligned, clamped and checked in the shop, and often match marked so they reassemble the same way in the field.
What standards apply to conveyor support steel?
Conveyors themselves follow ASME B20.1 for safety and often CEMA standards for design. The support structure is designed as structural steel to AISC 360, with welding commonly to AWS D1.1. Platforms, walkways and guardrails for maintenance access must meet OSHA walking working surface rules in 29 CFR 1910 Subpart D for general industry.